Machine Upgrades
The upgrades and options offered by Maplan have the following advantages for you:
- Extending life span of machine
- Increasing processing range
- Improving machine availability
- Reducing capital expenditures as compared to new machine purchase
Contact:
Thomas Samel
Phone: +43 2252 790 909 177
Email: thomas.samel@maplan.at
-
Main components:
- Exchange of electric cabinet
- Order specific software package
Lead time for offer: ~ 3 Weeks
Delivery time: ~ 16 Weeks
Cost of components: ~ € 35.000,-
Installation: € 6.000 - 9.000
Common options:
- Injection graphics € 2.200.-
- Logical Movement pneumatically € 750.-
- Logical Movement hydraulically € 2.660.-
- Cure² Interface € 2.600.-
- Special program on request depending on complexity
-
Main components:
- Base frame
- Spindle gear motor including brake and safety clutch
- Other mechanical components
- Wiring and software
Lead time for offer: ~ 1 Week
Delivery time: ~ 16 Weeks
Cost of components: ~ € 30.000,-
Assembly and commissioning: ~ € 4.000,-
-
Main components:
- Mechanics
- Hydraulics
- Wiring and software
Lead time for offer: 1 -2 Weeks
Delivery time: 10 - 14 Weeks
Cost of components: Order specific
Assembly and commissioning: ~ € 3.500
-
Main components:
- Main console
- Vertical or horizontal module (for vertical or horizontal clamping unit)
- Brush head
- Electric or pneumatic drive option for brush head and axis movements are available
Lead time for offer: ~ 1 Week
Delivery time: 10 - 12 Weeks
Cost of components: Order specific
Assembly and commissioning : ~ € 2.500,-
-
Main components:
- Stuffer
- Connection parts stuffer -machine
- Hydraulic components
- Conversion kit for machine covers
Lead time for offer: ~ 3 Weeks
Delivery time: 14 - 16 Weeks
Cost of components: ~ € 35.000,-
Assembly and commissioning: ~ € 6.000,-
|